Get the building constraints before finalising the programme: permitted working hours, lift protection, debris removal, noisy-work restrictions, water or power shutdown arrangements, and access to shared risers. A contractor can sequence the apartment perfectly on paper and still lose time...
Financing deserves its own timeline. Buyer approval, property assessment and document processing are separate dependencies, so an optimistic conversation with a lender is not the same as a completed financing path.