    Prague warehouse renovation: contingency on CZK 9,955,000 budget

    Combining the points above, I’d request three revisions from each bidder: a priced scope matrix, a programme linked to decisions and permits, and a list of provisional allowances. Then compare the fixed work separately from uncertain items. If one contractor refuses to expose assumptions, the...
  2. K

    Prague warehouse renovation: contingency on CZK 9,955,000 budget

    On financing, I agree with keeping it outside the works contingency. Track construction risk and time-related financing exposure separately, because a permit or procurement delay can increase the latter without changing the contractor’s scope. A monthly cash-flow forecast from each bidder would...
  3. K

    Prague warehouse renovation: contingency on CZK 9,955,000 budget

    Also ask which materials are already specified and which are placeholders. Long-lead electrical items, windows or energy-upgrade components could move the programme even when their purchase price is allowed. The bids should state who orders them, when decisions are required and whether...
  4. K

    Prague warehouse renovation: contingency on CZK 9,955,000 budget

    Nina’s question matters. I would also ask each contractor to define the electrical allowance precisely: distribution board, cabling, outlets, lighting, testing and making good after new runs. If they have only allowed to inspect the existing installation, the eventual repair bill is still an...
  5. K

    Prague warehouse renovation: contingency on CZK 9,955,000 budget

    Before choosing a contingency, put both bids into the same line-by-line schedule. “Electrical checks” could mean an inspection in one price and inspection plus remedial work in the other. The same problem applies to plumbing and energy upgrades. For an older warehouse with limited...
  6. K

    Contingency and hidden risks for a 245 m² Prague renovation

    One more question for the surveyor: where can plumbing actually be inspected without major opening-up? Visible fittings tell you little about concealed runs. The same applies to electrical checks—clarify whether the allowance is only for testing or includes remedial work and replacement of...
  7. K

    Contingency and hidden risks for a 245 m² Prague renovation

    Is the building vacant during the works, and are the residential and commercial areas served by the same utilities? That could affect sequencing more than the finishes. I’d also want to know whether kitchens and bathrooms remain in their current positions, because moving services can quickly...
  8. K

    Contingency and hidden risks for a 245 m² Prague renovation

    For an early budget like this, I’d tentatively carry 15–20% until the electrical condition, plumbing routes and moisture risks are clearer. Ask every contractor to list exclusions in writing, especially opening and making good walls, waste removal, access equipment and repairs discovered after...
  9. K

    Mixed-use unit versus serviced apartment in Prague: ownership costs and rental yield

    A simple stress test may settle it. Give each option the same rent assumptions, then add one vacant period, a rise in recurring charges and a separate irregular-cost line. For the mixed-use unit, leave the planned work as an explicit unknown rather than quietly treating it as zero. If the seller...
  10. K

    First-time buyer in Prague: how much cash buffer after closing at CZK 8,932,000?

    I’d protect the emergency fund first rather than treating the full CZK 510,400 as money available for the condo. Next, ring-fence known move-in costs, the first mortgage payment and service charges. Repairs should then follow the inspection: safety or water-related issues before cosmetic work...
  11. K

    Mixed-use unit versus serviced apartment in Prague: ownership costs and rental yield

    I’d separate its costs into three groups: recurring management charges, costs triggered by occupancy or turnover, and exceptional building or furnishing expenses. Read what the management arrangement actually includes rather than relying on one headline fee. Also model a period with no rental...
  12. K

    Mixed-use unit versus serviced apartment in Prague: ownership costs and rental yield

    The repeated mention of work without a price would concern me more than the property label. Ask what the work covers, whether quotations exist, how much is already held in shared-building reserves and how contributions are divided. A healthy-looking yield can disappear quickly if the purchase is...
  13. K

    Hello from Berlin — real estate agent focused on duplexes

    My reading order would now be: local board for terminology, first-purchase and legal checklist discussions for process, renovation and management threads for hidden costs, then mortgage and investment modelling. Keep your advertised-versus-completed-price work as a separate research strand so...
  14. K

    Hello from Berlin — real estate agent focused on duplexes

    I’d actually begin with first-purchase questions rather than data. Those threads tend to expose costs and process steps that asking-price charts omit. After that, build a simple comparison table showing advertised price, known completion price where available, condition, location, dates and...
  15. K

    Wanted: habitable 2-bedroom villa in Munich up to €289,800

    I was wondering the same. If the architectural label matters less than private residential use, saying so could widen the field. If it is essential, leave it firm and expect fewer approaches.
Back
Top