I’d sequence intrusive checks and any moisture remedy first, then plumbing and electrical work, followed by energy upgrades that disturb walls or ceilings. Flooring and final paint should be late.
Ask about material lead times before fixing the programme, especially where kitchen or bathroom...
Investigate before final pricing wherever there are visible signs, persistent smells, staining or inaccessible wet areas. You may not need widespread opening-up: ask the surveyor where targeted inspection would materially reduce uncertainty.
For plumbing, find out where the main runs and...