    Contingency and hidden risks for a €240,400 Utrecht renovation

    I would not choose the contingency percentage before separating estimates from fixed quotations. A 15% reserve can still be inadequate if the kitchen price excludes electrical alterations, plumbing diversions or making good; it may be excessive once those items are properly investigated. Build...