Renovation budget for a 200 m² warehouse in Warsaw

runsAndEmber

Homeowner
Established
The absence of an extension initially made this look straightforward, but the existing fabric may be the expensive part. I’m assessing a PLN 591,200 renovation allowance for a 200 m² Warsaw warehouse, including new kitchen and bathroom areas, finishes, electrical assessment and some energy improvements.

Before treating that number as workable, I want to establish whether there is moisture behind finishes, whether plumbing routes are accessible and whether any structural repairs are likely once surfaces are opened. I’m also concerned that material lead times could disrupt the order of work. What should the surveyor investigate, what exclusions should contractors price explicitly, and how much of the budget would you keep untouched for discoveries?
 
At this stage I would hold roughly 15% outside the quoted works, rather than letting it disappear into allowances. “Electrical checks” is too vague: ask whether the price includes testing only, remedial work, distribution-board changes and making good afterward. Also get explicit exclusions for waste removal, access equipment, temporary services and repairs after opening floors or walls.
 
What will the warehouse be used for after renovation, and is the kitchen domestic-style or more intensive? Those details could change the electrical, ventilation and drainage assumptions substantially. I’d also establish whether the plumbing is exposed or under the slab. If routes are unknown, a neat bathroom allowance can become misleading very quickly.
 
I wouldn’t choose one contingency percentage before doing targeted investigation. Fifteen percent may be comfortable after opening-up work, but it could be thin while the slab, roof and drainage routes remain unknown. No extension does not necessarily mean no structural repair.

I’d inspect for moisture after wet weather if possible, examine roof and wall junctions, and agree a few controlled openings. Then revise the contingency instead of treating it as a permanent lump sum.
 
Sequencing will probably save more than negotiating finishes. I’d go: condition survey and service mapping; limited opening-up; confirm room layouts and equipment loads; settle any permit responsibility; then issue the same scope and exclusions schedule to each contractor.

Ask bidders to identify long-lead materials and the latest decision date for each. Otherwise a delayed door, electrical component or bathroom item can hold up several trades.
 
The phrase I would challenge is “moderate energy upgrades.” Have each item named and priced separately—insulation, doors, heating or ventilation changes—because they interact with moisture and condensation risk. The same applies to electrical work: testing, design changes, installation and final verification should not sit behind one vague line. Ask who coordinates those interfaces and what happens if existing conditions prevent the proposed detail.
 
One addition to my previous point: keep an owner-controlled contingency and require written approval before it is used. Ask the contractor now for a complete exclusions list plus unit prices or a clear basis for likely unknowns, such as opening and reinstating floor areas. That makes later discussions about hidden plumbing or damp repairs much less subjective, while still allowing the design to proceed.
 