I’m testing a preliminary all-in renovation budget of €87,870 for a 50 m² new-build flat in Berlin. The scope covers the kitchen, bathroom work, flooring, painting, electrical checks and moderate energy upgrades. There is no extension or planned structural work.
My main concern is not finish selection but hidden conditions and sequencing: electrical scope that expands after inspection, limited plumbing access, moisture issues, contractor exclusions, and materials or permits delaying the programme.
What contingency percentage would you carry at this stage, and would you keep it separate from allowances for finishes and appliances? I’d also appreciate a short list of questions for the surveyor and contractors that would expose the biggest unknowns—particularly who pays for opening up and making good, what is explicitly excluded, realistic material lead times, and whether any approvals could affect the start date.
My main concern is not finish selection but hidden conditions and sequencing: electrical scope that expands after inspection, limited plumbing access, moisture issues, contractor exclusions, and materials or permits delaying the programme.
What contingency percentage would you carry at this stage, and would you keep it separate from allowances for finishes and appliances? I’d also appreciate a short list of questions for the surveyor and contractors that would expose the biggest unknowns—particularly who pays for opening up and making good, what is explicitly excluded, realistic material lead times, and whether any approvals could affect the start date.