Seoul 35 m² studio: setting contingency before surveys

knitsAndAtlas

Homeowner
Established
₩250,900,000 is the figure driving this decision, because it is a large preliminary budget for a 35 m² Seoul studio before access and existing conditions have been confirmed. The planned renovation includes the kitchen, bathroom areas, flooring, painting, electrical checks and some energy improvements, without an extension.

A generous contingency sounds safe, but it could hide an incomplete scope; a smaller one preserves cash but leaves little room for concealed pipe or moisture problems. What would alter the percentage for you? I plan to ask about plumbing access, waterproofing, electrical capacity, structural implications, material lead times, exclusions and permit timing. I also need accessibility layouts and clearances agreed early so they are not revised after work begins.
 
Until access and existing conditions are clearer, I would keep roughly 20% ring-fenced rather than burying it in finish allowances. That is a planning choice, not a Seoul rule.

Does the ₩250,900,000 include design fees, appliances, disposal, approvals and the tax treatment of contractor prices? Ask each bidder to list exclusions and assumptions separately, especially wall opening, electrical panel work, pipe replacement, waterproofing repairs and making good after inspections.
 
I’d focus on the building before choosing that percentage. Confirm with management what approvals are needed, permitted working times, lift or stair protection, debris routes, utility shut-offs and any limits on noisy work. Those constraints can break an otherwise sensible sequence.

Also ask contractors to identify long-lead materials and name an acceptable alternative now. A contingency fund does not help much if the kitchen is delayed and blocks flooring, painting or final electrical work.
 
A caveat to the moisture-survey idea: one dry reading can give false comfort. Ask where they will test, what visual signs they are looking for, and whether any limited opening-up is possible with permission.

Plumbing access may be the larger uncertainty in such a small studio. Can drains and supply lines be reached from inside the unit, a shared shaft or another property? Also clarify whether “bathrooms” means multiple wet areas. That affects waterproofing, sequencing and any accessibility layout far more than the floor area alone suggests.
 
Agreed on plumbing access, though I would not authorize opening anything until ownership and building permissions are clear. A useful next step is to send the same written scope to all contractors and require three separate figures: base work, priced optional risks, and contingency items that cannot yet be priced.

For electrical work, replace “checks” with explicit questions: what will be tested, what remains untouched, and what findings would trigger extra work? Once moisture, pipe routes, electrical boundaries and approval timing are documented, you can reconsider the 20% reserve instead of trimming it simply because the headline budget feels large.
 