Contingency and hidden-risk questions for a 220 m² Bengaluru townhouse renovation

kit_reese

Homeowner
Established
I can either hold back a sizeable reserve now and reduce the working scope, or keep more of the ₹8,077,000 available for the renovation and risk being caught by concealed defects. Neither feels sensible without better evidence.

This is a 220 m² Bengaluru townhouse needing work to the kitchen, wet areas, floors, decoration and electrical system, along with some energy-efficiency measures. I am not proposing an extension, although unexpected structural repairs still need to be ruled out. Which areas would you open up first to check moisture, pipe access and hidden services, and how would you set the contingency before contractor prices come back?
 
I’d initially model 15–20% contingency, then revise it after investigation. The lower end only makes sense if drawings, access and the condition of concealed services are reasonably clear. Ask every bidder to state exclusions for demolition, debris removal, waterproofing repairs, electrical replacement beyond testing, plumbing inside walls, and making good after openings.
 
How old is the townhouse, is it occupied, and are the kitchen and bathrooms staying in their present locations? Those facts could change the risk more than the floor area. Also clarify what “electrical checks” buys you: inspection and testing only, replacement of unsafe sections, or an allowance for broader rewiring?
 
One more missing detail: has there been visible dampness, repeated bathroom leakage or terrace-water intrusion? Fresh paint can obscure the extent of moisture. I would ask for moisture observations around wet rooms, external walls and roof or terrace junctions before agreeing to a flooring and painting sequence.
 
I’m less comfortable choosing one contingency percentage before the scope is unpacked. A large percentage can still disappear into one plumbing or waterproofing discovery. Keep separate allowances for concealed electrical work, plumbing access, moisture repairs and minor structural making-good, while retaining a smaller general reserve for ordinary changes.
 
That’s fair. The percentage is useful for the overall funding plan, but Rosa’s separate allowances make the tender more informative. I’d arrange limited exploratory openings where they can be made safely, then issue the same scope and exclusions schedule to each contractor. Otherwise one price may include wall repairs and testing while another quietly omits them.
 
Sequencing deserves its own contractor discussion: investigation and strip-out first, then concealed plumbing and electrical decisions, moisture treatment and drying, wet-area work, flooring, joinery, and final paint or touch-ups. Ask which materials have long lead times, when dimensions can be confirmed, and whether any planned work needs approval. Permit timing depends on the exact work and local requirements, so confirm it rather than assuming “no extension” means no process.
 
For contractor comparisons, request a room-by-room price breakdown plus a written list of assumptions. Useful questions include who protects retained areas, who stores materials, how hidden-condition changes are priced, what evidence supports a variation, and whether the programme allows inspections before walls or floors are closed. Also identify which decisions must be made before demolition and which can wait.
 
I would not order everything early merely to avoid lead-time problems. Appliances, tiles and standard fittings may be selected early, but custom joinery or items dependent on finished dimensions should wait until concealed work is understood. Confirm storage and damage responsibility too. The safer plan is to identify long-lead items early, then release each order only when its dimensions and interfaces are settled.
 