Contingency and hidden risks for an 810 sq ft Birmingham apartment renovation

round_workshop

Property investor
Established
I want a straightforward renovation with enough cash left to deal with surprises. The obstacle is that access and hidden services could disrupt even a modest scope.

My early budget is £48,780 for an 810 sq ft Birmingham apartment, covering a new kitchen and bathrooms, flooring, decoration, electrical checks and some energy improvements. There is no extension. What percentage would you hold separately as contingency? I’d also welcome specific questions for the surveyor and contractor about plumbing access, quote exclusions, building permissions and how delays should be handled before dates are agreed.
 
I’d start with 15% contingency and consider 20% if the plumbing and electrical routes cannot be inspected before work begins. Keep it outside the contractor’s quoted sum rather than allowing it to disappear into upgrades. Ask specifically what is excluded: making good after opening walls, waste removal, protection of common areas, access restrictions and VAT.
 
A few missing facts could change that answer: how old is the building, which floor is the apartment on, and will it be empty during the work? Also, can the main plumbing runs and consumer unit be inspected now? I’d check the lease or building-management requirements before fixing dates, particularly for noisy work, deliveries and anything affecting shared services.
 
Sequence the investigation before ordering the kitchen or flooring. I’d want moisture readings around both bathrooms and external walls, an electrical assessment that states whether remedial work is included, and clarity on where plumbing isolation points are located. Then agree who pays for opening up and reinstatement if concealed pipework cannot be assessed visually.
 
I’m not convinced a blanket 20% is automatically useful. With no planned structural work, it may encourage a loose quote instead of better definition. Split the uncertainty into allowances: electrical remedials, plumbing access, moisture repairs and building-related delays. If a contractor refuses to price or cap any of those after inspection, that tells you where the real exposure sits.
 
That’s fair, but “moderate energy upgrades” needs defining before reducing the contingency. Insulation, ventilation, heating controls and window-related work can interact with moisture and decoration even without structural alterations. I’d ask for a room-by-room scope showing what gets disturbed, what gets tested afterward, and whether final painting includes areas opened for services.
 
Build the programme backwards from the items and permissions that could hold everything else up. Confirm material lead times before demolition, and ask building management how long any required approvals normally take rather than assuming contractor availability sets the start date. The quote should also state responsibility for deliveries, storage, lift or stair protection, working hours and removal of old fittings.
 
Given the unknowns, I’d get three things before treating £48,780 as dependable: a written electrical scope, an access plan for bathroom and kitchen plumbing, and a contractor schedule listing exclusions and client-supplied items. Then stress-test the budget at both 15% and 20% contingency. The difference is useful evidence for deciding whether further inspection is worth paying for now.
 