readsAndMeter
Property investor
The ARS 101,100,000 budget looks workable only if the concealed services do not produce major surprises. My specific concern is coordinating access to plumbing and wiring without repeatedly damaging completed areas.
This is a 165 m² mixed-use building in Buenos Aires, with work planned to the kitchen, bathrooms, floors and decoration, plus electrical assessment and modest efficiency improvements. There is no proposed extension. At this early stage, how much contingency would you keep outside the main contract? I would also welcome suggestions for inspection questions that reveal moisture, service access and likely material delays, as well as contractor exclusions for opening walls and making them good again.
This is a 165 m² mixed-use building in Buenos Aires, with work planned to the kitchen, bathrooms, floors and decoration, plus electrical assessment and modest efficiency improvements. There is no proposed extension. At this early stage, how much contingency would you keep outside the main contract? I would also welcome suggestions for inspection questions that reveal moisture, service access and likely material delays, as well as contractor exclusions for opening walls and making them good again.