I have now put together a first-pass budget, but it has raised a sequencing question: how much uncertainty should be removed before I choose the finishes? The total is £34,860 for an 810 sq ft coastal home in Birmingham, with work planned to the kitchen and bathrooms as well as new flooring, decoration, electrical assessment and some energy improvements. There is no extension in the plan.
Would 10% be enough for surprises, or is 15–20% more realistic for this mix of work? I want the surveyor and contractors to identify moisture and plumbing access issues, define what happens if the electrical assessment finds defects, and list anything excluded from making good. Material lead times could also affect the order of work, so what should be confirmed before I commit to the budget?
Would 10% be enough for surprises, or is 15–20% more realistic for this mix of work? I want the surveyor and contractors to identify moisture and plumbing access issues, define what happens if the electrical assessment finds defects, and list anything excluded from making good. Material lead times could also affect the order of work, so what should be confirmed before I commit to the budget?