CLP 120,600,000 is my early allowance for renovating a 230 m² warehouse in Santiago, but too much of the existing condition is still unverified. The works would update the kitchen and washrooms, renew surfaces, review the electrical installation and improve energy performance. I am not proposing an extension.
Before selecting finishes, I want to test the building and the estimate. Which inspections would best uncover structural or moisture problems, and what should contractors be required to state about exclusions, sequencing and long-lead materials? I’d also like views on a sensible contingency before those checks are complete.
Before selecting finishes, I want to test the building and the estimate. Which inspections would best uncover structural or moisture problems, and what should contractors be required to state about exclusions, sequencing and long-lead materials? I’d also like views on a sensible contingency before those checks are complete.