Patch and paint in the wrong order — the turn killer nobody budgets for

The turn that always runs over for us is never the big repair. It is the patch-and-paint.

The problem: a wall gets patched on Monday, painted on Tuesday before the patch is dry, and by Thursday the patches are flashing through the paint. Now the painter is back for a second coat, the flooring crew is waiting, and the move-in date has not moved.

What works for us now:

- Patch first, on day one. Every wall, every hole, all of it — before anything else is scheduled in the room.
- Let the patches dry fully, sand them, and spot-prime every patch. A patch that is not primed will flash through the top coat, every time.
- Paint only after the primer is dry. Two coats on the walls, and the touch-up can stays with the unit — the exact bucket, labelled, under the sink.
- Clean last. The final clean runs top to bottom after the paint is done, not before.

The order matters more than the paint. When the sequence slips, the whole turn slips.

How do you sequence patch and paint in your turns — and what is the step that usually gets skipped when the schedule gets tight?
 