Renovation budget for a 1,400 sq ft retail unit in Birmingham?

ember.full

Homeowner
Established
I’d like to keep the renovation within £366,900, but the unknown condition of the building makes that figure difficult to trust. The Birmingham unit is 1,400 sq ft, and the intended work includes kitchen and bathroom fitting, new finishes, electrical testing and some energy-efficiency improvements. I am not proposing an extension.

Even so, a project described as non-structural can change quickly if opening up reveals movement, damp, failing services or inadequate support beneath existing fittings. Is £366,900 a sensible starting budget only with a sizeable contingency, and how large would you make it before surveys and contractor investigations?

I’d also welcome a practical list of what should be inspected or exposed before commitment, particularly around wiring, pipework, moisture entry and any structural alterations left by previous occupiers.
 
At this early stage I’d provisionally carry around 15%, then try to reduce it once opening-up work and surveys have clarified the building. Ask every contractor for a written exclusions list, not just a scope and price. In particular: making good after investigations, access equipment, service isolations, waste removal, work outside normal hours and temporary facilities. Those omissions can undermine comparisons between tenders.
 
Is the unit vacant, and what kind of kitchen is intended? A light staff kitchen and a customer-facing food operation create very different service and sequencing questions. I’d also establish where drains and water supplies actually run, whether access is possible from above or below, and whether there are any visible signs of moisture around external walls or former plumbing points.
 
I’m wary of choosing one contingency percentage before the scope is separated into known and unknown work. “Electrical checks” is especially vague: does the allowance cover inspection only, identified remedial work, changes to distribution, or any issue with the incoming supply?

The same applies to plumbing access. Price investigation and opening-up as an early package, then hold distinct allowances for electrical remediation, drainage and moisture repairs. Otherwise the contingency becomes a hiding place for incomplete contractor scope.
 
A practical next step would be a risk-and-sequence meeting before tender. Put surveys and opening-up first, then list dependencies: required approvals, structural confirmation for any new penetrations or heavy equipment, electrical remediation, plumbing and moisture work, energy upgrades, kitchen installation, and finishes.

Ask tenderers to state lead times, assumptions and exclusions against that same list. Also split the £366,900 into defined works, provisional allowances and contingency. That will show whether the budget is genuinely cautious or simply carrying several unknowns twice.
 