I can either hold a large contingency now or narrow it before the hidden conditions are understood, and neither option feels satisfactory. The working figure is £286,800 for a 1,940 sq ft Birmingham retail unit, with internal work to the kitchen, washrooms, floors and decoration, plus investigation of the electrics and some efficiency measures. There is no planned extension.
The finishes are not my main worry. Access to plumbing and drainage, damp, electrical remedial work, trading or access restrictions, and vague contractor exclusions could all disrupt the sequence. Material lead times may do the same. Which surveys should come before tender, and what should bidders price separately so the contingency is not disguising an incomplete scope?
The finishes are not my main worry. Access to plumbing and drainage, damp, electrical remedial work, trading or access restrictions, and vague contractor exclusions could all disrupt the sequence. Material lead times may do the same. Which surveys should come before tender, and what should bidders price separately so the contingency is not disguising an incomplete scope?