AED 532,000 is the preliminary figure I am testing for a 115 m² new-build flat in Dubai. Two contractors have returned very different prices, which makes me suspect they are not allowing for the same work.
The renovation includes a kitchen, bathrooms, new floors, painting, electrical work and modest energy improvements, with no extension. I plan to have both firms complete one itemised schedule showing materials, labour, approvals, protection, disposal and making good. The electrical section also needs to distinguish testing from moving sockets, lights or appliance feeds.
Before setting the contingency, what else should be fixed in writing? I am particularly concerned about material lead times, waterproofing, concealed services and exclusions that later become variations, rather than upgrading the finishes.
The renovation includes a kitchen, bathrooms, new floors, painting, electrical work and modest energy improvements, with no extension. I plan to have both firms complete one itemised schedule showing materials, labour, approvals, protection, disposal and making good. The electrical section also needs to distinguish testing from moving sockets, lights or appliance feeds.
Before setting the contingency, what else should be fixed in writing? I am particularly concerned about material lead times, waterproofing, concealed services and exclusions that later become variations, rather than upgrading the finishes.