Renovation budget for a 150 m² townhouse in Osaka - first time doing this

PatientAtlas

Architect
Verified Pro
If I set the contingency too low, concealed work could force cuts halfway through the renovation; if I set it too high without investigation, the ¥20,350,000 budget will not tell me much.

This is a preliminary allowance for a 150 m² Osaka townhouse. The intended work includes the kitchen and bathrooms, new flooring and paint, checks to the electrical installation, and some energy improvements. I am not proposing an extension, although the existing structure may still affect the scope.

Rather than choose one contingency percentage now, I am considering a staged approach. First I would investigate moisture, structural condition, plumbing routes and electrical capacity. Then I would ask contractors to identify exclusions, opening-up allowances, permit dependencies and long-lead materials before revising the reserve.

Which findings would justify reducing that reserve, and which would make you keep more aside? I would be particularly interested in how people distinguish a genuinely fixed item from work likely to return later as a variation.
 