Renovation budget for a 155 m² villa in Sydney?

AishaSlate

Homeowner
Established
Before I ask contractors to turn this into firm quotes, I need to decide whether A$115,600 is the working budget or the absolute ceiling. The project is a 155 m² older Sydney villa, covering the kitchen, bathrooms, floors, painting, electrical assessment and some energy improvements. I am not planning an extension or other deliberate structural work.

Reducing the visible scope would be easier to reverse than discovering late plumbing, waterproofing or moisture damage after the walls are opened. What contingency would you keep outside the quoted work, and which targeted inspections would be worth arranging first? I would also ask contractors to state their assumptions about access, sequencing, wall repairs and anything excluded from the price.
 
I’d be uncomfortable carrying less than roughly 15% contingency on an older building, and more if access beneath floors or behind wet-area walls is unclear. Ask every contractor to list exclusions rather than only inclusions: electrical remediation beyond checks, damaged plumbing, waterproofing substrate repairs, asbestos or other hazardous-material handling, wall make-good and permit-related delays. Also ask which assumptions their price relies on.
 
Would you keep that contingency outside the A$115,600, or reduce the working scope so the total cannot exceed it? I’m also wondering whether targeted openings around the bathrooms and kitchen would be more useful than a broad visual inspection, assuming they can be made safely and with permission.
 
Outside it, if A$115,600 is the current scope estimate. Otherwise the contingency is already spent on paper.

I wouldn’t assume targeted openings settle everything, though. They may reveal local moisture or plumbing access but miss deteriorated wiring elsewhere. Before opening anything, map where services probably run and have the relevant trades explain what would trigger rewiring, pipe replacement or structural input. Those trigger points matter more than a reassuring inspection.
 
Get the programme discussed alongside the price. Confirm what must be investigated first, when kitchen and bathroom materials need ordering, whether flooring waits until wet work is complete, and who carries delay risk if hidden conditions stop the job. Also establish early whether any part of the final scope needs approval in Sydney, because permit timing can disrupt an otherwise sensible sequence. A staged budget with explicit hold points would be safer than releasing the whole renovation at once.
 