Renovation budget for a 160 m² duplex in Zurich / school catchment

talia.cole

Property investor
I need to decide soon enough to keep the renovation aligned with the school timetable, but rushing the contractor choice could create a longer delay later. The working budget is CHF 335,200 for a 160 m² duplex in Zurich.

The planned work covers the kitchen, bathrooms, floors, decoration, an electrical review and some energy improvements. There is no intended extension. Two contractors have nevertheless returned very different totals for what should be comparable work.

Before selecting one, I want to separate items that can wait from risks that could stop the programme entirely. Which inspections would you arrange for moisture, accessible plumbing and the electrical installation, and how would you test material lead times and trade sequencing? I would also welcome views on setting a contingency once both quotations have been normalised.
 
I would not treat the gap between the two quotes as your contingency. First put both bids into the same line-by-line format and identify exclusions, provisional allowances and assumptions about existing services. Carry a separate reserve against the more complete comparable scope.

Ask each contractor what discovery would most likely change their price, who pays for opening up and making good, and whether kitchen, bathroom and electrical work can proceed without one trade blocking another.
 
One missing fact: will the duplex be vacant during the work? That can materially affect sequencing even without changing the finish specification. Also, are plumbing risers, drainage routes or other services shared with the rest of the building? If access depends on common areas or another unit, the programme may be less controllable than either quotation suggests.
 
The surprising part is that the higher quotation may contain no more protection than the cheaper one. I understand why using it as the cautious budget feels sensible, but a large total can still rely on vague allowances or omit difficult opening-up work.

I would first verify the wet areas, visible pipework, moisture signs and electrical board, then give both contractors the findings and the same schedule of questions. Any proposed layout alteration should also be checked for structural implications even though no extension is planned. Product specifications and delivery assumptions can be changed later; concealed service problems and structural decisions are much harder to reverse. Compare the revised written scopes rather than treating either original total as the safe figure.
 
Make a short risk schedule before negotiating: electrical remedial work, concealed plumbing, moisture repairs, structural implications, permit responsibility and long-lead materials. For each item, record whether it is inspected, included, excluded or still an allowance.

Then ask both contractors for an updated price and sequence against that schedule, including decision deadlines for the kitchen, bathrooms and flooring. If the school timetable creates a hard move date, distinguish essential work needed before occupation from finishes that could wait rather than forcing every uncertainty into one programme.
 