Renovation budget for a 180 m² new-build flat in Bangkok

timo.grove

Homeowner
Established
I’ve set an initial budget of THB 6,525,000 for renovating a completed 180 m² Bangkok flat, but I still cannot explain the large gap between two contractor quotes. The planned work includes new kitchens and bathrooms, floor and wall finishes, electrical testing and some efficiency improvements; I am not proposing an extension or other major structural change.

Before selecting a contractor, I want both prices tested against an identical scope. Which exclusions should be clarified first, and how much reserve would you keep outside the quoted sum? Plumbing access, hidden damp, work sequencing and long-lead materials worry me more than finish upgrades. Building approvals and restrictions could also affect the programme.
 
I would provisionally hold 10–15%, but not use contingency to excuse an unclear quotation. First put both bids into the same room-by-room schedule and require separate figures for labour, materials, testing, protection and waste removal. Also ask whether electrical “checks” mean visual inspection only or actual testing and remedial work. Have both contractors listed every exclusion?
 
Not yet. Both priced from the same broad scope, but I don’t have comparable line-by-line exclusions, which may explain more than the headline difference. I’ll ask them to define the electrical testing, plumbing access and making-good after any opening-up. The flat is complete, so I also need to establish what can be inspected without damaging finished areas before award.
 
The line-by-line exclusions should narrow the gap, but one question still comes first: what has each contractor assumed about opening finished surfaces? One may expect to reuse every plumbing point, while the other may have included cutting into a wall or floor and restoring it afterward.

Ask for a limited pre-contract inspection covering drainage and wet-area falls, reachable pipe connections, moisture near bathrooms and windows, the electrical panel and the circuits needed for the kitchen. Also confirm any limits on drilling or chasing. Each contractor should state who pays for exploratory access, making good and any additional work revealed, before a contingency percentage is chosen.
 
Sequencing could create another large gap. Confirm when final kitchen and bathroom dimensions are taken, which items must be ordered before demolition, and whether substitutions need your approval. Flooring should not arrive before moisture conditions and preceding wet work are acceptable. I’d also ask the building management about working hours, lift protection, deliveries and approval timing before accepting either contractor’s programme.
 
Make a comparison sheet with one row for every room and another section for shared items: site protection, temporary services, debris removal, electrical testing, plumbing pressure or leak checks, waterproofing responsibility, final cleaning and defect correction. Mark each row included, excluded or provisional.

Keep contingency outside the contract sum and require written approval before it is used. Otherwise ordinary omissions can quietly be presented as unforeseen work. Material lead-time risk is better handled through an early procurement list than through a larger cash reserve.
 
Given that clarification, I’d keep the 10–15% allowance during tendering, then consider reducing it once access assumptions, exclusions and approvals are settled. Split it mentally into hidden-condition money and owner-change money; don’t let finish changes consume the amount reserved for plumbing, moisture or electrical surprises. The cheapest useful next step is getting both contractors to return the same completed scope-and-exclusions table.
 