Homeowner
I can either accept quotes with different exclusions or delay the appointment until every bid follows the same schedule, and neither option feels comfortable. The overall project figure is ₩1366,000,000, including a preliminary renovation allowance of ₩497,700,000 for 190 m² of student housing in Seoul.
The planned work includes kitchens, bathrooms, floors, painting, electrical inspection and remedial items, plus limited energy improvements; no extension is intended. Finish levels are not my main concern. Moisture around wet areas, concealed plumbing, the true electrical scope, material lead times and whether the building remains occupied could all disrupt the sequence.
Would you ask bidders to reprice against one common scope before setting a contingency? I’m also considering targeted moisture checks and opening selected plumbing access points, but would like to know what other findings should be verified before choosing a contractor.
The planned work includes kitchens, bathrooms, floors, painting, electrical inspection and remedial items, plus limited energy improvements; no extension is intended. Finish levels are not my main concern. Moisture around wet areas, concealed plumbing, the true electrical scope, material lead times and whether the building remains occupied could all disrupt the sequence.
Would you ask bidders to reprice against one common scope before setting a contingency? I’m also considering targeted moisture checks and opening selected plumbing access points, but would like to know what other findings should be verified before choosing a contractor.