Renovation budget for a 2,150 sq ft mixed-use building in Birmingham?

DirectCairn

Homeowner
Established
I want the £82,490 budget to remain workable without stripping out the useful upgrades, but hidden work could upset it quickly. The project is a 2,150 sq ft mixed-use building in Birmingham, with refurbishment to the kitchen, bathrooms, floors and decoration, plus electrical assessment and some energy improvements. There is no extension.

The finishes are not intended to be costly; access, damp and the order of the trades concern me more. How much should remain outside the quoted budget for genuine surprises? I would also like to know which investigations should happen before final pricing, and which exclusions—particularly electrical remedial work, plumbing access and making good—need to be written into each quotation.
 
At this stage I would carry roughly 15% rather than the thinnest possible contingency, but keep it separate from items that simply have not been priced. Ask each contractor to state assumptions and exclusions in writing, particularly making good after electrical or plumbing work, waste removal, access equipment and protection of occupied areas.

Also establish whether the electrical figure means inspection only or includes any remedial work. That wording could conceal a large gap.
 
The distinction between contingency and unpriced work is helpful. The electrical allowance currently needs clarifying, as do VAT treatment and making good across the different quotations.

Would you investigate moisture before asking for final contractor prices, or let the main contractor open limited areas during the job? I’m wary of paying for speculative opening-up, but equally wary of discovering damp after flooring and decoration have started.
 
Investigate before final pricing wherever there are visible signs, persistent smells, staining or inaccessible wet areas. You may not need widespread opening-up: ask the surveyor where targeted inspection would materially reduce uncertainty.

For plumbing, find out where the main runs and isolation points are, whether bathroom and kitchen routes are accessible, and who pays for opening and reinstating walls or floors. Those answers affect both cost and sequence.
 
I’d sequence intrusive checks and any moisture remedy first, then plumbing and electrical work, followed by energy upgrades that disturb walls or ceilings. Flooring and final paint should be late.

Ask about material lead times before fixing the programme, especially where kitchen or bathroom work depends on specific components. Permit or building-control timing may also affect the start, so confirm what approvals apply to the mixed-use arrangement rather than assuming a non-structural scheme has none.
 
I disagree slightly with choosing 15% now. A percentage can create false comfort when the scope still says “electrical checks” and “moderate energy upgrades.” Neither describes a priced deliverable.

First turn those phrases into defined work, separate optional upgrades from required repairs, and obtain a list of exclusions. Then set contingency against the remaining unknowns. If access is poor or moisture remains unexplained, the reserve should reflect that specific exposure rather than the building’s total area alone.
 
That is fair. A practical next step would be a short pre-tender schedule with four columns: included work, assumed condition, exclusions and responsibility for making good. Issue the same schedule to every bidder so their numbers are comparable.

Before appointment, ask who coordinates trades, what can run concurrently, which materials must be ordered early, how discoveries are priced, and whether programme changes carry additional cost. The surveyor should also flag any apparent structural alteration or movement even though no extension is proposed.
 