The difficult part is comparing quotes when each contractor leaves out something different. I am working with a preliminary budget of €194,400 for a 225 m² detached home in Utrecht, covering new kitchen and bathroom work, floors, decorating, electrical inspection and some energy improvements. I am not proposing an extension.
The finish level is fairly moderate; uncertainty around existing services and the order of work worries me more. Moisture behind finishes, inaccessible pipework or electrical remedial work could affect several later trades. Permit timing could also disrupt the programme if any part of the scope requires approval.
Would you set the reserve only after putting every quote into a common scope, or carry a provisional allowance now? I would also welcome specific questions for the surveyor and bidders that would expose the largest exclusions before contracts are agreed.
The finish level is fairly moderate; uncertainty around existing services and the order of work worries me more. Moisture behind finishes, inaccessible pipework or electrical remedial work could affect several later trades. Permit timing could also disrupt the programme if any part of the scope requires approval.
Would you set the reserve only after putting every quote into a common scope, or carry a provisional allowance now? I would also welcome specific questions for the surveyor and bidders that would expose the largest exclusions before contracts are agreed.