The immediate problem is that the contractor quotes do not cover the same scope, so the totals are not yet comparable. The project is a 70 m² coastal home in Athens, and my working renovation allowance is €202,000.
The work would include a new kitchen and bathrooms, floors, paint, electrical testing and some energy improvements. I am not planning an extension, but concealed moisture or inaccessible plumbing could still alter the job substantially. Permit timing may also affect the order of work.
Would you set the contingency only after the surveyor has clarified those risks, rather than applying a standard percentage now? I would also like to know what wording to request on plumbing access, remedial electrical work, moisture sources, reinstatement and responsibility for permit delays.
The work would include a new kitchen and bathrooms, floors, paint, electrical testing and some energy improvements. I am not planning an extension, but concealed moisture or inaccessible plumbing could still alter the job substantially. Permit timing may also affect the order of work.
Would you set the contingency only after the surveyor has clarified those risks, rather than applying a standard percentage now? I would also like to know what wording to request on plumbing access, remedial electrical work, moisture sources, reinstatement and responsibility for permit delays.