I’d like to complete the essential renovation within €167,600, but hidden moisture or structural work could make that unrealistic. The property is a 75 m² villa in Paris, with kitchen and bathroom work, new flooring and paint, electrical investigation and moderate energy improvements in the preliminary scope. There is no planned extension.
Cosmetic items can become a later phase, whereas unsafe electrics, leaks or active damp cannot. Before choosing a contingency percentage, what missing information would most change it: evidence of moisture, access to the plumbing, the meaning of the electrical allowance, or the possibility that opening floors and walls reveals structural issues?
I’m also considering asking contractors to separate firm prices, provisional sums and exclusions, then provide a sequence for investigations, approvals and long-lead materials. Would that be enough to set a realistic reserve, or should the first contract cover investigation and essential work only before I commit to the finishes?
Cosmetic items can become a later phase, whereas unsafe electrics, leaks or active damp cannot. Before choosing a contingency percentage, what missing information would most change it: evidence of moisture, access to the plumbing, the meaning of the electrical allowance, or the possibility that opening floors and walls reveals structural issues?
I’m also considering asking contractors to separate firm prices, provisional sums and exclusions, then provide a sequence for investigations, approvals and long-lead materials. Would that be enough to set a realistic reserve, or should the first contract cover investigation and essential work only before I commit to the finishes?