Renovation budget for a 90 m² mixed-use building in Sydney

LightStory

Construction professional
Established
The difficult part is allowing for work that cannot be priced properly until finishes are opened up. I’m reviewing an A$289,800 renovation allowance for a 90 m² mixed-use building in Sydney, with no extension or other structural addition planned.

The intended work includes the kitchen, bathrooms, floors, decorating, an assessment of the electrics and some modest energy improvements. Before settling on finishes, I want to pin down whether the electrical allowance covers only testing or also remedial work, and how plumbing routes, damp, demolition, access and making good will be treated. What contingency seems realistic at this stage? I’d also appreciate suggestions for exposing contractor exclusions and showing permit dependencies and long-lead orders in the programme.
 
For that scope, I would provisionally carry 15–20% until the existing services and concealed areas are better understood, then revisit it once quotes are properly itemised. Ask whether electrical work means inspection only or includes switchboard, wiring and compliance-related rectification. Also have contractors state assumptions about plumbing routes, waterproofing, moisture damage, demolition, waste removal, access and making good. Those exclusions are where an apparently complete price can unravel.
 
I wouldn’t choose the contingency percentage before clarifying occupancy and access. Will either the commercial or residential part remain in use during the work? Staging around occupants can change both time and cost without adding any visible scope. I’d also ask for a programme showing permit dependencies and the order dates for long-lead materials. Separate allowances for genuinely unknown work from fixed-price items, rather than hiding everything inside one contingency figure.
 