Second opinion on ₩165.7m renovation budget for 50 m² serviced apartment in Seoul

bikesAndEcho

Homeowner
Established
I’ve added a modest allowance for energy improvements, which raises a new question about whether the overall budget is protecting me from the right risks. The working figure is ₩165,700,000 for a 50 m² serviced apartment in Seoul, including kitchen and bathroom work, new floors, decorating and electrical checks. I am not planning an extension or other major structural addition.

Better finishes are easy to trim later. Moisture behind a bathroom wall, restricted plumbing access or electrical work that expands after opening surfaces could change the project entirely. Sequencing may also become expensive if building approvals or long-lead materials hold up later trades.

What level of contingency would you allow, and what should I ask the surveyor and contractor to investigate before the scope is fixed?
 
Before choosing a contingency percentage, ask for an exclusions schedule. Specifically: who pays for opening and reinstating walls, inaccessible plumbing, failed electrical components, moisture treatment, waste removal and work required by building management? Also have the contractor separate provisional amounts from fixed-price items. A large total can still be fragile if those categories are vaguely described.
 
One missing fact is whether the apartment will remain operational during the work. If access hours, noise limits or shared-service shutdowns restrict sequencing, labour and programme risk may matter more than finishes. I’d also ask which materials must be ordered first, what can be substituted, and whether any bathroom, kitchen or electrical work must wait for building approval.
 
I would not assume that “no extension” means no structural risk. Demolition can reveal previous alterations, moisture around wet areas or routes that cannot accommodate the planned services. That said, simply adding a generous contingency may hide a weak scope. First arrange targeted opening-up where permitted, record existing electrical and plumbing conditions, then obtain a revised programme showing dependencies and contractor exclusions. Keep contingency separate rather than letting it disappear into upgraded finishes.
 