Second opinion on £95,010 renovation budget for an 860 sq ft Edinburgh apartment

even_thread

Homeowner
Established
The difference between the two quotes is large enough that I no longer think finish selections are the main risk. I am working with a preliminary figure of £95,010 for an 860 sq ft Edinburgh apartment, covering a new kitchen and bathrooms, floors, decoration, electrical review and some energy-efficiency work. There is no extension in the scope.

I suspect the outcome will depend more on what each contractor has omitted and what appears once work starts. I would appreciate views on a sensible contingency, especially where plumbing routes or floor preparation are uncertain. I also plan to ask about permit timing, access arrangements, waste removal and any provisional allowances. What should a surveyor inspect before I try to compare the bids on equal terms?
 
I would start with a 15% contingency, but only after putting both quotes into the same line-by-line format. Ask each contractor to identify exclusions, provisional sums and assumptions about electrical remedial work, plumbing access, floor preparation and waste removal. A cheaper total can simply mean more items have been left undefined.
 
What age and floor is the apartment, and is there any history of leaks from above or around external walls? Moisture and inaccessible plumbing could change the job far more than the visible finishes. I’d also ask whether either quote assumes the kitchen and bathrooms can reuse their present service routes.
 
I’m not convinced a flat 15% solves the problem. If one tender has vague allowances, the contingency becomes a substitute for proper pricing. First ask both firms to price an identical schedule and state who pays for opening up and reinstating walls or floors. Then keep contingency for genuinely concealed conditions rather than known omissions.
 
Sequencing deserves its own conversation with each contractor. Ask for a simple programme showing surveys or approvals, ordering, strip-out, first-fix electrical and plumbing work, drying time, finishes and final testing. Also ask which materials have long lead times and what happens if they arrive late. Their answers may explain part of the price difference.
 
Even without an extension, confirm whether any proposed internal changes touch structural elements, shared services or parts of the building that may need consent. Edinburgh properties vary, so permit and building-specific timing should be checked for this apartment rather than assumed. A targeted survey of moisture, floors and intended opening-up areas could narrow the biggest unknowns.
 
Before selecting either contractor, send both the same short list: fixed price versus allowance for each item, electrical work included after the checks, plumbing access assumptions, moisture repairs, making good, protection of common areas, debris removal, lead times and responsibility for approvals. If they revise their bids against that list, you’ll be comparing scope rather than headline totals—and can set the contingency around what remains uncertain.
 