Stress-testing a MX$2,072,000 renovation budget for 105 m² in Mexico City

ravi_wilde

Homeowner
Established
If the scope is wrong, the MX$2,072,000 figure could distort both the renovation decision and the expected exit date. I am assessing a 105 m², five-bedroom small multifamily property in Mexico City, and two contractors have produced very different prices from what was supposed to be the same brief.

The proposed work covers the kitchen and bathrooms, new floor finishes, redecoration, checks and possible repairs to the electrical system, and limited efficiency improvements. There is no planned extension. My main concern is not choosing finishes; it is discovering moisture, plumbing or wiring problems after work has begun and then losing time by reopening completed areas.

I need to decide whether to investigate first or request matching bids first. For example, identical allowances would still be misleading if one contractor assumes existing wiring can remain and the other includes remedial work. Would targeted moisture tracing, electrical checks and limited opening-up be the sensible first step? After that I could require room-by-room prices showing exclusions, disposal, access, sequencing, permit responsibility and material lead times, with ordinary contingency kept separate from unknown conditions.
 
I would not choose the contingency percentage until both contractors rewrite their bids against the same room-by-room scope. Ask each to identify exclusions, assumptions, demolition and disposal, plumbing access, electrical remedial work, material lead times and permit responsibility. A low bid that excludes opening walls or repairing disturbed finishes is not really the same scope. Also separate ordinary contingency from money reserved for genuinely unknown conditions.
 
Is the building vacant during the work, and are the bathrooms or kitchens stacked? Those details could change the sequence substantially. Plumbing access from another unit, occupied rooms, or having to reopen newly finished surfaces can hurt both cost and timing.

I’d also push back slightly on focusing first on bid comparison. Moisture tracing and targeted opening-up may be more valuable before asking for revised prices. Otherwise both contractors may simply price different guesses.
 
That is a fair caveat. I’d combine the two approaches: investigate moisture, visible cracking, service capacity and likely plumbing routes first, then issue one clarified scope to both contractors. Require them to state what happens if concealed damage or structural work appears, rather than burying it in a broad allowance.

For the exit schedule, map permit timing, investigations, procurement, demolition and inspections separately. A fallback based on one uninterrupted construction period looks fragile if any long-lead material is selected.
 