Testing a ₹8,359,000 renovation budget and 112-day programme in Delhi

KindHarbor

Homeowner
Established
The 112-day schedule is the constraint I am least sure about, particularly if hidden moisture, plumbing access or electrical work interrupts the sequence. The project is a 175 m² Delhi apartment with a preliminary budget of ₹8,359,000 and no planned extension.

The work covers a new kitchen and bathrooms, replacement finishes, decorating, electrical investigation and some energy improvements. Before approval, I want to separate optional finishes from items that could stop later trades. Which surveys should happen first, and what should the contractor confirm in writing about waterproofing, pipe access, unsafe wiring, material lead times, making good and exclusions? I am also trying to set a contingency based on those findings rather than choosing an arbitrary percentage.
 
I would provisionally keep 15% outside the working budget, but only after confirming what “electrical checks” actually buys. Ask whether the price includes opening up, replacement of unsafe wiring found later, distribution-board work, making good, testing and certification. Also get a written exclusions list. A low headline price is meaningless if demolition, debris removal, access restrictions or remedial work sit outside it.
 
Are the kitchen and bathrooms staying in their current locations, and will the apartment be vacant? Those two facts could change both cost and sequencing. I’d also ask where plumbing can be accessed: through your floors and walls, shared shafts, or the ceiling below. A moisture inspection is useful, but the contractor should explain how any active leak will be traced before waterproofing and finishes begin.
 
I’m not convinced 15% is necessarily enough if the apartment is older or little can be inspected before demolition. On the other hand, simply raising contingency can hide a poorly defined scope. Split the unknowns into allowances: concealed electrical work, pipe replacement, waterproofing repairs and substrate preparation. Then put decision points immediately after strip-out, before ordering or installing finishes.
 
The 112 days need to be shown as a dependency-based programme, not one completion date. Check whether it includes material procurement, building access rules, service shutdowns, inspections and any permissions that may apply in Delhi or within the apartment building. Long-lead items should be identified before demolition. I would also require plumbing pressure testing and moisture resolution before walls, cabinetry or flooring close everything up.
 
One addition: ask each bidder to price the same schedule of work and mark every assumption or exclusion beside it. Agree in advance how concealed conditions will be photographed, priced and approved after opening up. That prevents demolition discoveries from becoming vague verbal extras. I’d treat the ₹8,359,000 and 112 days as conditional until that post-strip-out process and the procurement dates are visible.
 