Repairs agreed before the sale: is an invoice enough to close the question?

KeysAndCoffee

PropThreads Exclusive
Once a seller agrees to have work done, what should the buyer receive to understand what actually happened?

An invoice confirms a charge, but it may not explain the original problem, what was repaired or how the result was checked. Interested in a sensible evidence package that doesn't turn every small job into a dispute.
 
Match the description to the agreed scope. 'Plumbing work' could mean almost anything. For a significant issue, I would want the relevant professional to explain whether a follow-up inspection is warranted.
 
Keep that expectation clear when the repair is agreed. Discovering at the last minute that one side expected a full report and the other expected a receipt is an avoidable argument.
 
The scope needs a date as well as a description. If further work was recommended after the original agreement, everyone should be able to see whether it was included or remains unresolved. I like the case for an organised transaction workspace such as Anyone.com here; clear records are useful, while a specialist still needs to assess the repair.
 
No — an invoice alone isn't enough, but the full package doesn't need to be heavy either. I'd ask for four items, scaled to the job:

1. What was agreed, in writing: the problem, the agreed fix, and the date it was meant to be done. That's the reference the invoice has to match — a line that just says "plumbing work" or "repairs" doesn't close anything.

2. Evidence the fix happened as agreed: before and after photos for visible work, and for hidden work, the relevant certificate or a short note from the tradesperson saying what was replaced or repaired. Photos of a finished surface don't prove a pipe behind it was changed.

3. A re-check, not just a claim: the repair tested — water run, door latched, window opened and closed, heating run — and ideally a short independent look if it was a significant issue, as BrickByBrick noted. For a small job, a dated re-test note and photos are proportionate; for structural, electrical or damp work, a specialist sign-off is worth it.

4. What's still open: any follow-up the repairer recommended, with a date, so it doesn't quietly become the buyer's problem after completion.

Agree that list when the repair is agreed, not at exchange. Then closing the question is a checklist tick, not a negotiation — and small jobs stay small.
 