Contingency and sequencing for a £215,500 London retail renovation

ReadyTable

Property investor
Established
The fixed constraint is an 85-day programme, and I do not want an optimistic sequence to consume the cash contingency. The project is a 1,180 sq ft London retail unit with a preliminary renovation allowance of £215,500.

The planned work covers the kitchen, bathrooms, floors, decoration, electrical testing and moderate efficiency improvements. There is no intended extension, but concealed moisture, inaccessible plumbing, remedial electrical work or an unexpected structural issue could still disrupt both price and timing. One outstanding paperwork point also affects whether the fallback exit is realistic.

Would you keep unknowns outside the tender totals, or include defined provisional sums so bids remain comparable? My preference is to investigate service routes and damp first, obtain written exclusions and lead times, then release later design work only if the early findings support the budget. If they do not, I would simplify the specification before committing to the full scope.
 
I’d provisionally hold 15–20%, then release it only after intrusive areas and service routes are understood. Ask whether the electrical allowance covers testing alone or resulting remedial work, where plumbing can actually be accessed, and how moisture behind finishes will be investigated. Also request a written exclusions list and identify long-lead materials before accepting the 85-day sequence.
 
The distinction between testing and remedial electrical work is useful; the current budget headings could hide that gap. Would you keep the contingency outside the contractor’s stated budget, or ask bidders to include allowances for those unknowns? I’m concerned that burying everything inside one figure will make comparisons look cleaner than they really are.
 
I disagree with choosing a contingency percentage first. If bidders have different exclusions, 15% on each price does not make them comparable. Get the same scope and assumptions returned by all of them: opening-up work, making good, waste removal, access restrictions, service shutdowns and responsibility for permit-related delays. Then add an owner-held reserve separately. The unresolved paperwork item should also be treated as a go/no-go dependency, not absorbed into contingency.
 
Build the programme backwards from the deadline. Put approvals, opening-up, electrical and plumbing investigations, moisture drying if needed, and material orders ahead of finishes. Then mark which activities can genuinely overlap. If a late discovery can stop several trades, simplify that part of the design now rather than assuming extra labour will recover the time.
 
That gives me a better structure: normalise the bids through one assumptions-and-exclusions schedule, keep the reserve outside the contract figure, and avoid releasing it for design upgrades. I’ll also split the 85 days into dependencies rather than one continuous contractor programme. The unresolved item will remain a go/no-go point; I won’t make the fallback depend on an optimistic exit date.
 