The fixed constraint is an 85-day programme, and I do not want an optimistic sequence to consume the cash contingency. The project is a 1,180 sq ft London retail unit with a preliminary renovation allowance of £215,500.
The planned work covers the kitchen, bathrooms, floors, decoration, electrical testing and moderate efficiency improvements. There is no intended extension, but concealed moisture, inaccessible plumbing, remedial electrical work or an unexpected structural issue could still disrupt both price and timing. One outstanding paperwork point also affects whether the fallback exit is realistic.
Would you keep unknowns outside the tender totals, or include defined provisional sums so bids remain comparable? My preference is to investigate service routes and damp first, obtain written exclusions and lead times, then release later design work only if the early findings support the budget. If they do not, I would simplify the specification before committing to the full scope.
The planned work covers the kitchen, bathrooms, floors, decoration, electrical testing and moderate efficiency improvements. There is no intended extension, but concealed moisture, inaccessible plumbing, remedial electrical work or an unexpected structural issue could still disrupt both price and timing. One outstanding paperwork point also affects whether the fallback exit is realistic.
Would you keep unknowns outside the tender totals, or include defined provisional sums so bids remain comparable? My preference is to investigate service routes and damp first, obtain written exclusions and lead times, then release later design work only if the early findings support the budget. If they do not, I would simplify the specification before committing to the full scope.