How much contingency for a 160 m² Warsaw serviced-apartment renovation?

celine.archer

Homeowner
Established
I’m torn between holding a large contingency and reducing the specification before requesting firm prices. The first protects the plan from surprises; the second may leave more cash available but could still miss expensive work behind the finishes.

The working budget is PLN 216,900 for a 160 m² serviced apartment in Warsaw. It allows for new kitchen and bathroom work, replacement finishes, decorating, an electrical review and some energy improvements. I am not proposing an extension, though I still need to establish whether any layout changes affect the structure.

Which unknowns would you investigate before choosing the contingency? I’m particularly concerned about access to pipes, damp, the difference between checking the electrics and correcting defects, and costs omitted from the contractor’s scope. I also need a workable sequence for approvals, materials with long lead times and the intended exit date.

My preference is a staged decision: investigate the costly hidden items first, then either retain the design or cut optional finishes before work begins.
 
I would not choose one contingency figure until the electrical and plumbing assumptions are clearer. Ask whether the price includes opening and making good walls, replacing non-compliant wiring rather than merely checking it, waste removal, protection of common areas, and work discovered after removing bathroom finishes. Also request a room-by-room scope with explicit exclusions. Those answers will show whether the contingency is covering genuine unknowns or an incomplete quotation.
 
I agree on exclusions, but even a detailed quotation will not solve the sequencing risk. Before appointing anyone, ask who coordinates shutdowns and access, whether moisture testing happens before flooring is ordered, and which items have long lead times. Also clarify whether any planned changes require approvals and how that affects the programme. I’d keep two fallback lists: finishes that can be downgraded early, and work that cannot safely be deferred.
 