I would prefer to simplify the design before signing, but the concealed services are the obstacle. The preliminary budget is PHP 4,795,000 for a 180 m² one-bedroom condo in Manila, covering a new kitchen, bathroom work, floors, decoration, electrical investigation and modest efficiency improvements. No extension or structural addition is planned.
The finishes can be changed later; inadequate plumbing access, moisture or wiring discovered after demolition could force much more expensive decisions. How much contingency should remain outside the contract, and would you open selected areas before agreeing the price or use provisional allowances?
I also want an explicit exclusions list covering opening and reinstating walls, repairs found during checks, debris removal and delays while permits or building approvals are obtained. The paperwork currently blurs customary local practice with binding responsibility. I would rather stage the commitment around those findings than discover halfway through that an essential item belongs to neither party’s scope.
The finishes can be changed later; inadequate plumbing access, moisture or wiring discovered after demolition could force much more expensive decisions. How much contingency should remain outside the contract, and would you open selected areas before agreeing the price or use provisional allowances?
I also want an explicit exclusions list covering opening and reinstating walls, repairs found during checks, debris removal and delays while permits or building approvals are obtained. The paperwork currently blurs customary local practice with binding responsibility. I would rather stage the commitment around those findings than discover halfway through that an essential item belongs to neither party’s scope.