How much contingency for a PHP 4.795m condo renovation in Manila?

BenEast

Homeowner
I would prefer to simplify the design before signing, but the concealed services are the obstacle. The preliminary budget is PHP 4,795,000 for a 180 m² one-bedroom condo in Manila, covering a new kitchen, bathroom work, floors, decoration, electrical investigation and modest efficiency improvements. No extension or structural addition is planned.

The finishes can be changed later; inadequate plumbing access, moisture or wiring discovered after demolition could force much more expensive decisions. How much contingency should remain outside the contract, and would you open selected areas before agreeing the price or use provisional allowances?

I also want an explicit exclusions list covering opening and reinstating walls, repairs found during checks, debris removal and delays while permits or building approvals are obtained. The paperwork currently blurs customary local practice with binding responsibility. I would rather stage the commitment around those findings than discover halfway through that an essential item belongs to neither party’s scope.
 
I would start around 15% contingency, but keep it outside the contractor’s quoted sum and release it only for documented changes. Bathrooms, kitchen services and anything concealed behind finishes are where I’d focus the pre-work questions.

Ask who pays for opening and reinstating walls, replacing unsuitable wiring or pipework, debris handling, building-required working arrangements, and delays caused by approvals. Also request an exclusions list; a detailed scope without explicit exclusions can still leave large gaps.
 
Keeping the contingency separate makes sense. The current figure does not clearly distinguish investigation from repair: “electrical checks” is listed, but not what happens if the checks identify replacement work.

Would you ask for provisional allowances for that and plumbing access, or insist on opening selected areas before signing? I’m concerned that allowances could simply postpone the price discussion.
 
I’d open selected areas first where the condo management permits it, especially near wet areas and service routes. A provisional allowance is useful when access genuinely cannot be obtained, but it should state what quantity or task it assumes and how any difference will be priced.

I would not automatically raise the contingency just because the project is in Manila. A vague PHP 4.795m scope with 20% added can be less safe than a well-defined scope with 10–15%. Also confirm management requirements, work hours, delivery access and permit timing before agreeing to the programme; those may affect sequencing even when the physical work is straightforward.
 
Map the sequence before choosing where to cut finishes: investigation and approvals, demolition, concealed electrical/plumbing work, waterproofing and testing, then finishes and fixtures. Ask the contractor to attach responsibility, lead time and acceptance criteria to each stage.

For every line marked “by owner,” “if required” or “subject to site conditions,” get a price basis or a clear decision date. That should expose whether the PHP 4,795,000 is a buildable budget or mainly a finishes estimate with the difficult items deferred.
 