Renovation budget for a 180 m² warehouse in Rotterdam at €1,012,000 — one more sanity check

emery.gray

Developer
My preferred outcome is to renovate in stages without letting uncertain building work consume the whole reserve. The obstacle is that opinions on this Rotterdam warehouse are split, and too much of the scope remains based on assumptions.

The purchase price is €1,012,000 and the building is 180 m². I have pencilled in €250,200 for fitting out the kitchen and bathrooms, renewing surfaces, checking the electrical system and making moderate efficiency improvements. I am not proposing an extension, although I realise that does not eliminate the possibility of repairs to the existing structure.

Before proceeding, which investigations would best narrow the exposure from moisture, drainage, electrical capacity and opening floors or walls? I also want contractors to identify exclusions, provisional items and reinstatement work rather than burying them in a single total. I can absorb a contained overrun, but not a scope that remains undefined, so I am setting written conditions for pausing, proceeding or walking away.
 
I would initially reserve around 15–20%, but not treat that as permission to accept vague pricing. Ask each contractor to list exclusions, provisional sums, assumed access and who pays for opening and reinstating walls or floors. Moisture, inaccessible plumbing and an electrical installation needing more than “checks” could consume contingency quickly. Get those investigated before choosing finishes.
 
What is the warehouse’s current condition and intended use? A kitchen and bathrooms can mean minor replacement or entirely new service routes. I would want to know where drains run, whether floors must be opened, the state and capacity of the electrical installation, and whether there are signs of roof or ground-level moisture. “No extension” does not rule out expensive structural repairs.
 
A percentage can come later. First turn every identifiable uncertainty into either a priced allowance or a pre-contract investigation, which supports the distinction made above between a reserve and vague scope.

For example, drainage access, electrical capacity and the source of any damp should not all sit inside one contingency pot. Once those points have been tested, the remaining reserve can cover events that could not reasonably be defined beforehand.

I would also put approvals and long-lead materials onto the work sequence. Even if the building work itself does not expand, a delay can extend site costs and disrupt the order of trades.
 
That distinction is important. I would ask for a room-by-room scope plus a services schedule, then require bidders to price the same assumptions. For electrical work: what has actually been inspected, what remains subject to testing, and what would trigger rewiring? For plumbing: are routes visible, and is making good included? Otherwise the lowest total may simply contain the most omissions.
 
For the pause/proceed/walk-away list, I would make the triggers measurable before signing: unresolved moisture source, no credible access plan for drains, major electrical scope still undefined, contractor exclusions exceeding the reserve, or permit timing incompatible with the programme. The exact contingency matters less once several of those remain open simultaneously; at that point the budget is not yet dependable.
 