makeTheVale
Construction professional
The preliminary estimate is €352,800, but I am not ready to treat it as dependable for a 35 m² serviced apartment in Rotterdam. It covers work to the kitchen and bathrooms, floor finishes, decoration, electrical checks and some energy improvements. No extension or other planned structural work is included.
My hesitation is less about choosing finishes and more about what may be hidden behind the allowances. Plumbing access, moisture, making good and any structural intervention discovered during opening-up could change both cost and sequence.
Would you set the contingency only after limited investigative work, or carry a larger sum from the outset? I’d also appreciate a list of specific questions for the surveyor and contractor about exclusions, provisional prices and responsibility for concealed conditions.
My hesitation is less about choosing finishes and more about what may be hidden behind the allowances. Plumbing access, moisture, making good and any structural intervention discovered during opening-up could change both cost and sequence.
Would you set the contingency only after limited investigative work, or carry a larger sum from the outset? I’d also appreciate a list of specific questions for the surveyor and contractor about exclusions, provisional prices and responsibility for concealed conditions.