Sanity check on €352,800 renovation budget for a 35 m² Rotterdam serviced apartment

makeTheVale

Construction professional
The preliminary estimate is €352,800, but I am not ready to treat it as dependable for a 35 m² serviced apartment in Rotterdam. It covers work to the kitchen and bathrooms, floor finishes, decoration, electrical checks and some energy improvements. No extension or other planned structural work is included.

My hesitation is less about choosing finishes and more about what may be hidden behind the allowances. Plumbing access, moisture, making good and any structural intervention discovered during opening-up could change both cost and sequence.

Would you set the contingency only after limited investigative work, or carry a larger sum from the outset? I’d also appreciate a list of specific questions for the surveyor and contractor about exclusions, provisional prices and responsibility for concealed conditions.
 
Before choosing a contingency percentage, I would ask for a line-by-line reconciliation of that €352,800. For 35 m², the bigger danger is that an expensive allowance still omits key work. Have the contractor identify demolition, waste removal, temporary protection, electrical remedial work, plumbing access, drying, making good and VAT separately. Also ask which prices are fixed and which remain provisional.
 
What is known about the walls and floors around the bathrooms and kitchen? A visual inspection alone may not reveal moisture or where shared pipes can actually be reached. I’d ask whether limited opening-up is possible before the final price.

Also clarify whether the electrical item means inspection only or includes bringing defects found during that inspection into the contract sum. Those are very different scopes.
 
That distinction on the electrical scope is useful—I had been treating “checks” as though any resulting work was implicitly covered. I’ll separate investigation from remedial work and ask for the exclusions in writing. The same probably needs to happen for moisture testing and opening up around the plumbing.
 
I wouldn’t automatically add a large contingency to the full €352,800. If much of that figure consists of specified materials or other firm prices, applying the same percentage to everything can hide weak estimating rather than manage risk. Put contingency mainly against demolition, concealed services, moisture damage and reinstatement.

The sequencing question matters too: confirm material lead times before stripping out, and establish whether plumbing and electrical inspections must happen before surfaces are closed.
 
Agreed on separating the uncertain work, although I would still retain an overall reserve until investigations are complete. Ask the contractor for a simple programme showing demolition, surveys, first-fix services, drying time if moisture is found, inspections, finishes and commissioning. Every dependency should have a named assumption.

I’d also ask who is responsible for confirming any building-management requirements and whether Rotterdam permit timing affects any part of the energy or services work. That may be straightforward, but it should be confirmed locally rather than assumed. Finally, request lead times and latest order dates for the kitchen, bathroom items and flooring.
 
One more useful test: ask what event would entitle the contractor to charge extra, and how that extra would be priced and approved. A contingency is only useful if the change process prevents it from becoming an untracked second budget.
 