Setting contingency and sequencing for a €171,500 Dublin renovation

avery_gray

Construction professional
Established
Verified Pro
The 195 m² floor area is the detail that made me question whether €171,500 should be treated as a budget or only as the first stage of one. The Dublin project covers a kitchen, bathrooms, floors, decoration, electrical checks and moderate energy improvements, without an extension in the present scope.

I am considering a staged approach: first pay for surveys, access checks and any permit advice, then seek firm prices once the wiring, plumbing routes and moisture risks are better understood. If those checks are clean, the reserve could remain modest; if walls or floors must be opened, I would want the making-good work and a larger contingency priced separately. What contingency range would members keep outside the working sum, and what exclusions should contractors be required to identify? I also need to clarify how the building’s description as a studio and the position of the wet areas affect the scope.
 
I’d initially keep 15–20% outside the €171,500 rather than treating it as money available for upgrades. That is a planning allowance, not a prediction. The reserve could shrink once you know the condition of the wiring, where plumbing can be accessed and whether there is any active moisture problem. Ask contractors to price making good after opening walls and floors, not just the visible installation work.
 
One important detail: does “studio” mean an open-plan home, a work studio, or a mixed-use space? At 195 m², the layout and use could materially affect the electrical and ventilation scope. Are the kitchen and bathrooms staying where they are? Moving wet areas would make plumbing access and floor construction much more important.
 
That’s a fair question—the word “studio” is too vague for pricing purposes. I’ll replace it with a measured room and use schedule when requesting quotes. I’m also going to separate the base scope from the reserve rather than letting every contractor interpret the €171,500 as the target spend. Locations of services need to be confirmed before I freeze the tender scope.
 
Make the exclusions schedule as detailed as the priced work. I’d specifically ask who covers waste removal, access equipment, protection of retained areas, temporary services, testing, and repairs after electricians or plumbers open surfaces. Also establish whether taxes are included in every figure. Those omissions can make two apparently similar quotations impossible to compare.
 
For sequencing, investigate first, then settle the layout and service routes. Electrical and plumbing work should happen before plaster repairs, painting, flooring and fitted joinery. Any moisture source needs resolving before insulation or finishes conceal it. Ask about material lead times only after dimensions and specifications are stable; ordering early helps the programme, but ordering from assumptions creates expensive rework. Permit or approval timing should also be confirmed locally rather than assuming that no extension means no formal process.
 
I wouldn’t automatically add 20% and call the budget safe. A large percentage can disguise an undefined scope just as easily as a small one can understate risk. First obtain a condition survey, identify where limited opening-up would answer real questions, and have each contractor use the same scope and exclusions list. Then separate known work, provisional items and genuine contingency. If suspected structural alteration, cracking or significant moisture appears, get the appropriate specialist input before contractor pricing is treated as firm.
 