The AED 724,600 renovation allowance looks detailed on the surface, but concealed moisture is the part I cannot price with confidence. The property is a 70 m² mixed-use building in Dubai offered at AED 3,909,000, and the planned works cover the kitchen, bathrooms, floors, decoration, electrical inspection and modest energy improvements.
I am not proposing an extension, although I realise new service routes or changes around wet areas could still involve structural work. Rather than add one blanket reserve, would you split the contingency between plumbing or moisture discoveries, electrical remedial work and permit or lead-time delays?
I also plan to ask the surveyor where access or opening-up is needed, and have the contractor state whether testing, reinstatement, disposal and permit-related items are included. What else should be settled before treating the budget as reliable?
I am not proposing an extension, although I realise new service routes or changes around wet areas could still involve structural work. Rather than add one blanket reserve, would you split the contingency between plumbing or moisture discoveries, electrical remedial work and permit or lead-time delays?
I also plan to ask the surveyor where access or opening-up is needed, and have the contractor state whether testing, reinstatement, disposal and permit-related items are included. What else should be settled before treating the budget as reliable?