Setting contingency for a 70 m² Dubai mixed-use renovation

daily_porch

Property investor
Established
The AED 724,600 renovation allowance looks detailed on the surface, but concealed moisture is the part I cannot price with confidence. The property is a 70 m² mixed-use building in Dubai offered at AED 3,909,000, and the planned works cover the kitchen, bathrooms, floors, decoration, electrical inspection and modest energy improvements.

I am not proposing an extension, although I realise new service routes or changes around wet areas could still involve structural work. Rather than add one blanket reserve, would you split the contingency between plumbing or moisture discoveries, electrical remedial work and permit or lead-time delays?

I also plan to ask the surveyor where access or opening-up is needed, and have the contractor state whether testing, reinstatement, disposal and permit-related items are included. What else should be settled before treating the budget as reliable?
 
I would not settle on a single contingency percentage before some opening-up work. Separate the uncertainty into concealed plumbing and moisture, electrical remedial work, and approval or lead-time costs. Ask whether the contractor’s price includes testing, making good after access, waste removal and work outside normal hours. Is the building currently occupied, and will either use need to remain operational during the renovation?
 
The phrase “electrical checks” is too loose for a budget of this size. Does it mean inspection only, replacement of failed items, or upgrades needed for the proposed kitchen and mixed-use load? I’d want the scope to state who pays if testing reveals more work.

I also wouldn’t assume that no extension means no structural risk. Moving wet areas or cutting new service routes can still create structural questions.
 
I agree on tightening the electrical wording, but opening up everything first may be impractical. Start with targeted access around bathrooms, kitchen connections and any visible moisture staining, then price explicit provisional items rather than burying all uncertainty in contingency.

Before appointing anyone, get a written exclusions list, a room-by-room sequence, proposed material order dates, and confirmation of who handles building or authority approvals. Permit timing and long-lead materials can affect the programme even when the physical work is straightforward.
 