When should I arrange an independent inspection for a Lagos new build?

UmaBirch

Homeowner
I have the builder’s assurance that this Lagos new build will receive municipal approval, but I still do not know what that process checks in practice. The property is a 2-bed detached home, and my concerns are drainage, insulation and finish defects rather than approval alone.

When would a buyer-commissioned inspection have the most value: while there is still time to correct issues before completion, during the handover walk-through, or later within the defect period? Finding something such as poor drainage before the furniture arrives would be useful, but access and working utilities may limit what can be tested. I also need to retain enough cash for moving, the first mortgage payment, any initial service charges and an emergency fund.
 
I’d choose before completion, provided the builder allows access, then do your own careful walk-through at handover. Municipal approval and an inspection commissioned by the buyer do not necessarily answer the same questions. Earlier findings may also be easier to address before you move furniture in. Keep the report focused on visible condition, drainage and agreed finishes rather than assuming it can uncover everything.
 
What does your purchase agreement actually say about inspection access and the deadline for reporting defects? Timing advice is difficult without that. Also ask whether utilities will be working during the visit; some items cannot be meaningfully checked otherwise. I’d want dated photos and a written list that identifies the room or exterior area for each finding.
 
I’m not convinced an inspection before completion is automatically the best use of limited cash. If the home is still being finished, the report may mostly list incomplete work, and you could end up paying for another visit later. For a buyer whose emergency fund is already thin, a thorough handover inspection plus money reserved for immediate repairs and the insurance excess may be the better trade-off.
 
That caveat is fair, but it suggests asking for inspection prices and scope now rather than skipping it. Find out whether one fee can cover a pre-handover visit and a short return visit, then compare that with your moving costs, service charges if any, furniture plans and first mortgage payment. I’d delay nonessential furniture before draining the repair reserve. Whatever timing you choose, send findings promptly in writing and keep copies of the report, photos and the builder’s responses.
 
I'd think of it as three visits, not one, and price it that way — which is where DirectHarbor's suggestion of asking for a bundled fee helps.

1. Before finishes go on, if access allows. This is the only chance to see what will be hidden: pipework and wiring routes, waterproofing in wet areas, roof structure and drainage before ceilings and tiles cover them. A photo record at this stage is worth more than a long list later.

2. Pre-handover snagging, with utilities on. This is the visit most people mean by "inspection" — every door, window, tap, flush, socket and extractor tested, room by room, with dated photos and a numbered list, one defect per line. Agree in advance what the builder's defect-reporting deadline is, so findings go in in writing, promptly, as openTheRidge said.

3. A short return visit after you've moved in, and ideally after heavy rain. Doors swell, leaks show, and things that worked on a dry day fail under use. That visit is much cheaper than the first two and catches the items a handover walk-through can't.

If budget only stretches to one visit, make it the pre-handover one — but don't skip the photo record during construction if you can get access, even informally. And confirm in the purchase agreement that inspection access is allowed at those stages, and whether utilities will be running for the handover visit, because some checks can't be done meaningfully without them.
 